Release Process for OpenHIE V1.0 

From a process perspective, this release was a learning release.  The release process is expected to be matured for subsequent releases of OpenHIE.  The release process formed and discussed in several of the OpenHIE meetings.  See the following meeting notes for more information:  

Release Criteria:  

 The following criteria were defined for OpenHIE Release 1.0.  

  1. This release will have workflow specifications

  • Workflow must have a sponsor

  • Workflow must be documented
  • Workflow must have one or more reference implementations 
  • Workflow must be tested at the component level which includes IHE testing if applicable

      2.   The release also has other applicable documentation


OpenHIE V1.0 Process and timeline:  

The following is a general outline of the timing for OpenHIE V1.0:  

  1.  Sept 12 - Architecture community voted on workflows to be included

  2.  Nov. 30th – “Pencil’s down”  - workflows and individual software components will be completed 

  3.  Nov. – March - IHE testing, software and workflow modifications.  

  4.  April and May Integration Testing

  5.  May 15 – go live